Business Expanding enterprises of China's power industry in terms of a habit, also known as reported installed electrical connection. Its main meaning is to accept applications for customer use of electricity, according to the actual situation in power, for expanding electricity supply and related operations to meet customer electricity needs. Business sector after receiving the customer's client application, should according to the different nature of electricity, combined with power to investigate and study the circumstances and then determine the supply plan, organizational design and construction of power projects, check the customer's electrical equipment , a power supply contract signed until the equipment supply table. To complete the whole process of this work, called the Business Expanding, referred to as trade expanded.
First, Business Expanding the basic order and content
First, the main contents of business expansion
business expansion: the electric power supply and distribution enterprises in the receiving part, is the power of the pre-service behavior.
a) the process of business expansion: a user application for registration -3 -2 site inspection to determine admissibility of power supply plan for approval -5 -4 -6 reply to impose a fee on customers to design -8 -7 9 Construction Design Review - 10, signed a contract completion and acceptance of -11 -12 -13 archiving electronic equipment table then register for permanent residence.
b) business expansion process time limits for each link:
Supply Scheme respond to customers: 1) household does not exceed 5 working days (3 days). 2) low pressure does not exceed 10 working days (7 days). 3) high-voltage single power supply of not more than 1 month (15 days). Dual power of not more than 2 months (30 days)
design review period: 1) low for low-count, high for the low total in 10 working days. 2) 10KV high for high-design, dual power and green project in 15 working days. 3) 35KV and over-powered engineering drawings completed within 1 month.
final acceptance deadline: completion report received within 5 working days after the order arrangements for project acceptance.
installed electrical connection time table: Customers have the transmission conditions of 1) low-voltage does not exceed 5 working days. 2) High pressure does not exceed 10 working days. 3) residents to take power from the application of not more than 5 working days. (After acceptance by the electrical engineering, power transmission within 5 working days) * Figures in brackets for the provincial power company user commitment to the province in 2005.
supply solutions for validity: the validity of high-voltage power supply program for 1 year, low-voltage power supply scheme is valid for 3 months, late cancellation. Users need to be extended in exceptional cases the validity of the program when the power supply should be 10 days before the expiry date of the proposed power supply companies, power companies should be handled as the case may extend the procedures.
Second, change the electricity business
change the electricity business: means for changing the power from the two sides signed the
power to change the contents: volume reduction, relocation, change the power point, pressure change, suspend, temporarily changed, changed its name (transfer), transfer table, temporarily removed, change class, household, and households termination of electric and other projects.
for change the basic principles of electricity service:
1, by volume: volume reduction is the official electricity customers, due to a change in production and operation, taking into account the original with the capacitor is too large, not all use, in order to reduce expenditure on basic electricity or energy needs, the contract proposed to reduce electricity consumption for a change electricity capacity issues. Client application volume reduction must be within 5 business days prior to the power supply to apply the following provisions shall apply for power supply enterprises
1) must be the entire or the whole group to stop or replace the transformer for the small-capacity power transformer; power companies after the date of acceptance, according to the customer on the date of application volume reduction equipment sealed. From the date of sealing, the corresponding reduction in the original billing capacity of the basic tariff. But the customer is declared to be permanent or at least from the date of sealing of 2 years without electricity for recovery procedures,UGG bailey button, or after volume reduction capacity of less than the capacity to implement the provisions of the standard two part tariff should be changed to a single system electricity billing.
2) volume reduction period: minimum of not less than 6 months and not longer than 2 years;
3) volume reduction in the period to restore the electricity should be restored electricity for 5 days before the procedure, the basic tariff from the closing date of unsealed;
4) after the expiration of volume reduction and new clothes, compatibilization of customers, not for 2 years by content or suspended. If really necessary to continue to handle the content or suspended reduction, capacity reduction or suspension of some 50% of the basic tariff shall be charged.
5) volume reduction prior to the implementation of two part tariff of users, volume reduction still during the implementation of two part tariff.
6) within the time limit in the volume reduction, power supply enterprises to retain the right to use customers to reduce capacity, volume reduction over time for the restoration of electricity, they should be procedures for newly installed or compatibilizer.
2, relocation: official electricity customers, due to production and business reasons or municipal planning, to be the original migration of electricity by an electrical device at a variation of his power issues. Electricity customers to migrate applications address must be within 5 days prior to the power supply enterprises to apply.
1) site for sell electricity by end users, a new site priority for electricity;
2) relocation is not a new site after the original supply point, the new site for consumption by new electricity;
3) the new site after the relocation of power points in the original and the new site does not exceed the original capacity of electricity capacity, the new site without electricity for by newly installed, but due to the relocation cost borne by the user;
4) and should bear the default of 500 yuan each time use of electricity; belonging to other customers, should bear the use of every 5,000 electricity bill for breach of contract.
3, suspension: that electricity customers in the formal, due to production and business conditions change, need for temporary or seasonal change or equipment maintenance, electricity and other reasons, to save and reduce electricity costs, you need a short time to stop using part or all of the electrical equipment of a capacity to change electricity business.
1) customers in each calendar year, may apply for all or part of the suspension of electric power capacity of the two, shall not be less than 15 days each year, the cumulative pause time not more than 6 months . Seasonal electricity or as otherwise provided in the client countries, the cumulative pause time can be negotiated;
2) received by the transformer capacity of the basic tariff customers, electricity must be the entire suspension of the entire group of transformers stop running. Suspended accepting applications for power supply enterprises, according to the date of application for suspension of customers equipment sealed. From the date of sealing, the corresponding reduction in the original billing capacity of the basic tariff.